Evaluasi Kinerja Dump Truck di PT HPMU Kabupaten Ketapang
I will put the dimension here
Abstract
HPMU is a mining company and is located in Ketapang Regency, West Kalimantan Province. PT. HPMU has a production target of 360,000 tons/month. The realization of production sometimes does not reach the production target per month due to various factors including weather, availability of tools, use of tools, labor, and so on. This can be monitored in the mine control room, which is tasked with monitoring activities such as reporting ritase, ore mining, weighing, MGB hauling, reporting hours for repairs, reporting for fule filling, and reporting hours meter (HM). The monitoring results are used as a control and reference to analyze the level of production in the field so that if a problem occurs in production activities, it can be addressed immediately. This study aims to evaluate the performance using monitoring data from the mine control room. The calculation of the performance of the Hino type dump truck using data working hours, standby units, and repair hours. The performance evaluation of the means of transportation shows that dump truck (DT) with number 62 has the best performance among 5 dump truck units, with percentage values of mechanical of availability (MA), physical of availability (PA), use of availability (UA) and effective of utilization (EU) 88%, 91%, 75% and 65% respectively. While the DT 65 has the worst performance among 5 dump truck units with MA, PA, UA and EU 59% values, respectively 72%, 77%, 76% and 59%.
References
[2] Nurcahyo, D. (2018). Kemampuan Produksi Alat Muat Dan Alat Angkut Pada Kegiatan Penambangan Bauksit di PT. Cita Mineral Investindo. Tbk. Site air upas, Kabupaten Ketapang, Kalimantan Barat. 17-20.
[3] Pradjosumarto, P. (1993). Pemindahan tanah mekanis. Bandung: Jurusan Teknik Pertambangan Institut Teknik Bandung.
[4] Silalahi, R. (2017). Evaluasi Produktivitas Alat Angkut Untuk Mengoptimalkan Controlling Muatan pada Kegiatan Penambangan Batugamping, di PT Semen Bosowa Maros, Desa Baruga, Kecamatan Bantimurung, Kabupaten Maros, Provinsi Sulawesi Selatan. Prosiding Teknik Pertambangan. Universitas Islam Bandung.
[5] Sulistianto, B. (2008). Peralatan tambang dan penanganan material. Bandung: Program Studi Teknik Pertambangan Fakultas Teknik Pertambangan dan Perminyakan Institut Teknik Bandung.
[6] Suwandhi, Awang. 2004. Perencanaan Jalan Tambang, Diktat Perencanaaan Tambang Terbuka. Bandung: Jurusan Teknik Pertambangan UNISBA
[7] Arif, Irwandy, dan Adisoma, G.S. 2002. Buku Ajar Perencanaan Tambang. Bandung: Institut Teknologi Bandung.
[8] Rochmanhadi, 1985, Alat Berat dan Penggunaannya, YBPPU, Jakarta.
[9] Yanto, 2006, Pemindahan Tanah Mekanis, Jurusan Teknik Pertambangan, UPN Veteran Yogyakarta.
[10] Saputra, H. 2020. Analisis Produktivitas Alat Muat dan Alat Angkut dengan metoda Overall Equipment Effectiveness (OEE) di PT. Tanito Harum, Tenggarong, Kalimantan Timur. Skripsi Prodi Teknik Pertambangan, UPN Veteran Yogyakarta.
Copyright (c) 2022 Sartika
This work is licensed under a Creative Commons Attribution 4.0 International License.